Sec. 141. Economic order quantity contracting authority for F–35 joint strike fighter program
587 words·~3 min read·
/bill/116/hr/6395/eas/section-141·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
The Secretary of Defense may enter into one or more contracts, beginning with the fiscal year 2020 program year, for the procurement of economic order quantities of material and equipment for the F–35 aircraft program for use in procurement contracts to be awarded for such program during fiscal years 2021 through 2023. The total amount obligated in fiscal year 2021 under all contracts entered into under subsection
(a)shall not exceed $493,000,000. Before entering into a contract under subsection (a), the Secretary shall make each of the following findings with respect to such contract: The use of such a contract will result in significant savings of the total anticipated costs of carrying out the program through annual contracts. The minimum need for the property to be procured is expected to remain substantially unchanged during the contemplated contract period in terms of production rate, procurement rate, and total quantities. There is a reasonable expectation that, throughout the contemplated contract period, the Secretary will request funding for the contract at the level required to avoid contract cancellation. There is a stable design for the property to be procured, and the technical risks associated with such property are not excessive. The estimates of both the cost of the contract and the anticipated cost avoidance through the use of an economic order quantity contract are realistic. Entering into the contract will promote the national security interests of the United States. Except as provided in subsection (e), the Secretary of Defense may not enter into a contract under subsection
(a)until 30 days after the Secretary certifies to the congressional defense committees, in writing, that each of the following conditions is satisfied: A sufficient number of end items of the system being acquired under such contract have been delivered at or within the most recently available estimates of the program acquisition unit cost or procurement unit cost for such system to determine that the estimates of the unit costs are realistic. During the fiscal year in which such contract is to be awarded, sufficient funds will be available to perform the contract in such fiscal year, and the future-years defense program submitted to Congress under section 221 of title 10, United States Code, for that fiscal year will include the funding required to execute the program without cancellation. The contract is a fixed-price type contract. The proposed contract provides for production at not less than minimum economic rates given the existing tooling and facilities. The Secretary has determined that each of the conditions described in paragraphs
(1)through
(6)of subsection
(c)will be met by such contract and has provided the basis for such determination to the congressional defense committees. The determination under paragraph
(5)was made after the completion of a cost analysis performed by the Director of Cost Assessment and Program Evaluation for the purpose of section 2334(f)(2) of title 10, United States Code, and the analysis supports that determination. Notwithstanding subsection (d), the Secretary of Defense may enter into a contract under subsection
(a)on or after December 1, 2020, if— the Director of Cost Assessment and Program Evaluation has not completed a cost analysis of the preliminary findings made by the Secretary under subsection
(c)with respect to the contract; the Secretary certifies to the congressional defense committees, in writing, that each of the conditions described in paragraphs
(1)through
(5)of subsection
(d)is satisfied; and a period of 30 days has elapsed following the date on which the Secretary submits the certification under paragraph (2).