§ 2347a. Determination of project completion
256 words·~1 min read·
/usc/title-33/section-2347aA research copy — for the controlling text, always check the official state or federal source. Not legal advice.
(a)In general The Secretary shall notify the applicable non-Federal interest when construction of a water resources project or a functional portion of the project is completed so the non-Federal interest may commence responsibilities, as applicable, for operating and maintaining the project.
(b)Non-Federal interest appeal of determination
(1)In general Not later than 7 days after receiving a notification under subsection (a), the non-Federal interest may appeal the completion determination of the Secretary in writing with a detailed explanation of the basis for questioning the completeness of the project or functional portion of the project.
(2)Independent review
(A)In general On notification that a non-Federal interest has submitted an appeal under paragraph (1), the Secretary shall contract with 1 or more independent, non-Federal experts to evaluate whether the applicable water resources project or functional portion of the project is complete.
(B)Timeline An independent review carried out under subparagraph
(A)shall be completed not later than 180 days after the date on which the Secretary receives an appeal from a non-Federal interest under paragraph (1).
(Pub. L. 113–121, title I, § 1010, June 10, 2014, 128 Stat. 1217.)
Connections2 cite this · traces to 2
Cited by 2 sections
public-private-law
statute-compilations
Traces to 2 documents
public-private-law
U.S. Code
1 reference not yet in our index
- 128 Stat. 1217
Citation graph
cites case law
§ 2347a
Determination of project completion
Pub. L.×1
Stat. Comp.×1
Stat.128 Stat. 1217
Cites 3Cited by 2 across 2 sources