## SEC. 1010 DETERMINATION OF PROJECT COMPLETION **[**[33 U.S.C. 2347a](/us/usc/t33/s2347a)**]** ###
(a)In General The Secretary shall notify the applicable non-Federal interest when construction of a water resources project or a functional portion of the project is completed so the non-Federal interest may commence responsibilities, as applicable, for operating and maintaining the project. ###
(b)Non-Federal Interest Appeal of Determination ####
(1)In general Not later than 7 days after receiving a notification under subsection (a), the non-Federal interest may appeal the completion determination of the Secretary in writing with a detailed explanation of the basis for questioning the completeness of the project or functional portion of the project. ####
(2)Independent review #####
(A)In general On notification that a non-Federal interest has submitted an appeal under paragraph (1), the Secretary shall contract with 1 or more independent, non-Federal experts to evaluate whether the applicable water resources project or functional portion of the project is complete. #####
(B)Timeline An independent review carried out under subparagraph
(A)shall be completed not later than 180 days after the date on which the Secretary receives an appeal from a non-Federal interest under paragraph (1).