Tap any paragraph to write a margin note. Your notes collect in the Desk below the text and file under cases with @. The side-by-side margin rail opens on a larger screen.

Code · U.S. Code · Title 30 - MINERAL LANDS AND MINING · CHAPTER 22— MINE SAFETY AND HEALTH · SUBCHAPTER III— INTERIM MANDATORY SAFETY STANDARDS FOR UNDERGROUND COAL MINES · § 867

§ 867. Grounding of equipment

402 words·~2 min read·/usc/title-30/section-867

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

(a)Metallic enclosed power conductors; metallic frames and other equipment; methods All metallic sheaths, armors, and conduits enclosing power conductors shall be electrically continuous throughout and shall be grounded by methods approved by an authorized representative of the Secretary. Metallic frames, casings, and other enclosures of electric equipment that can become “alive” through failure of insulation or by contact with energized parts shall be grounded by methods approved by an authorized representative of the Secretary. Methods other than grounding which provide no less effective protection may be permitted by the Secretary or his authorized representative.
(b)Frames of offtrack direct current machines; enclosures of related detached components The frames of all offtrack direct current machines and the enclosures of related detached components shall be effectively grounded, or otherwise maintained at no less safe voltages, by methods approved by an authorized representative of the Secretary.
(c)Stationary high-voltage equipment powered by underground delta systems The frames of all stationary high-voltage equipment receiving power from ungrounded delta systems shall be grounded by methods approved by an authorized representative of the Secretary.
(d)Repairs of high-voltage lines; exceptions High-voltage lines, both on the surface and underground, shall be deenergized and grounded before work is performed on them, except that repairs may be permitted, in the case of energized surface high-voltage lines, if such repairs are made by a qualified person in accordance with procedures and safeguards, including, but not limited to a requirement that the operator of such mine provide, test, and maintain protective devices in making such repairs, to be prescribed by the Secretary prior to the operative date of this subchapter.
(e)Deenergizing of underground power circuits on idle days; exceptions When not in use, power circuits underground shall be deenergized on idle days and idle shifts, except that rectifiers and transformers may remain energized.
(Pub. L. 91–173, title III, § 307, Dec. 30, 1969, 83 Stat. 780.)
Connections1 cite this · traces to 1
Cited by 1 section
statute-compilations
4 references not yet in our index
  • Pub. L. 91–173, title III, § 307
  • 83 Stat. 780
  • section 509 of Pub. L. 91–173
  • Pub. L. 91–173
Citation graph
cites case law
§ 867
Grounding of equipment
Stat. Comp.×1
Pub. L.Pub. L. 91–173, title III, § 307
Stat.83 Stat. 780
Pub. L.section 509 of Pub. L. 91–173
Pub. L.Pub. L. 91–173
Cites 5Cited by 1 across 1 source
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.