Code · CFR · Title 18 — Conservation of Power and Water Resources · Part 12 — Safety of Water Power Projects and Project Works · § 12.37

§ 12.37. Comprehensive assessment.

320 words·~1 min read·/us/cfr/t18/s§ 12.37·

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

A comprehensive assessment must include:
(a)Review of prior reports and analyses of record. The independent consultant team must review and consider all relevant reports on the safety of the development made by or written under the direction of Federal or state agencies, submitted under Commission regulations, or made by other consultants. The licensee must provide to the independent consultant team all information, reports, and analyses of record necessary to fulfill the requirements of this section.
(1)In addition to the requirements of § 12.35(a), the independent consultant team must have a full understanding of the risk associated with the project works.
(2)The independent consultant team shall perform a detailed review of the as-built drawings; monitoring data; and the methods, assumptions, calculations, results, and conclusions of the analyses of record pertaining to:
(i)Geology and seismicity;
(ii)Hydrology and hydraulics;
(iii)Stability and structural integrity of project works; and
(iv)Any other analyses relevant to the safety, stability, and operation of project works.
(b)Physical field inspection. The independent consultant team must perform a physical field inspection that complies with § 12.35(b).
(c)Review of surveillance and monitoring plan and data. The independent consultant team must perform a review of surveillance and monitoring plan and data that complies with § 12.35(c).
(d)Review of dam and public safety programs. The independent consultant team must perform a review of dam and public safety programs that complies with § 12.35(d).
(e)Supporting Technical Information Document. The comprehensive assessment shall include a review of the Supporting Technical Information Document.
(f)Potential failure mode analysis. The comprehensive assessment shall include a potential failure mode analysis.
(g)Risk analysis. The comprehensive assessment shall include a risk analysis. The Regional Engineer may, for good cause shown, grant a waiver of the requirement to complete a risk analysis. Any petition for waiver under this paragraph must be filed in accordance with § 385.207 of this chapter.
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.