572.12 Time of filing against railway.
62 words·~1 min read·
/ia/chapter-572-mechanic-s-lien/572-12·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
Where a lien is claimed upon a railway, the subcontractor shall have ninety days from the last day of the month in which such labor was done or material furnished within which to file the claim therefor.
[R60, §1851; C73, §2137; C97, §3092; C24, 27, 31, 35, 39, §10281; C46, 50, 54, 58, 62, 66, 71, 73, 75, 77, 79, 81, §572.12]