[§269-146] Hawaii electricity reliability surcharge; authorization; cost recovery.

331 words·~2 min read·/hi/chapter-269/269-146

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

[§269-146] Hawaii electricity reliability surcharge; authorization; cost recovery.
(a)The commission may require, by rule or order, that all utilities, persons, businesses, or entities connecting to the Hawaii electric system, or any other user, owner, or operator of any electric element that is a part of an interconnection on the Hawaii electric system shall pay a surcharge that shall be collected by Hawaii's electric utilities. The commission shall not contract or otherwise delegate the ability to create the Hawaii electricity reliability surcharge under this section to any other entity. This surcharge amount shall be known as the Hawaii electricity reliability surcharge.
(b)Amounts collected through the Hawaii electricity reliability surcharge shall be transferred in whole or in part to any entity contracted by the commission to act as the Hawaii electricity reliability administrator provided for under this part.
(c)The Hawaii electricity reliability surcharge shall be used for the purposes of ensuring the reliable operation of the Hawaii electric system and overseeing grid access on the Hawaii electric system through the activities of the Hawaii electricity reliability administrator contracted under section 269-147; provided that amounts collected under the Hawaii electricity reliability surcharge shall not be available to meet any current or past general obligations of the State.
(d)The commission may allow an electric utility to recover appropriate and reasonable costs under the Hawaii electricity reliability surcharge for any interconnection to the Hawaii electric system, including interconnection studies and other analysis associated with studying the impact or necessary infrastructure and operational requirements needed to reliably interconnect a generator, as well as from electric utility customers through a surcharge or assessment subject to review and approval by the commission under section 269-16.
(e)Nothing in this section shall create or be construed to cause amounts collected through the Hawaii electricity reliability surcharge to be considered state or public moneys subject to appropriation by the legislature or be required to be deposited into the state treasury. [L 2012, c 166, pt of §2]
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.