40-360.43. Activity in close proximity to lines; clearance arrangements; procedure; payment; notice

278 words·~1 min read·/az/title-40/40-360-43

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

A. If any person or business entity desires to temporarily carry on any function, activity, work or operation in closer proximity to any high voltage overhead line than permitted by this article, the person or business entity responsible for performing the work shall promptly notify the public utility operating the high voltage overhead line. The person or business entity may perform the work only after satisfactorily mutual arrangements, including coordination of work and construction schedules, have been made between the public utility operating the lines and the person or business entity responsible for performing the work.
Arrangements may include placement of temporary mechanical barriers to separate and prevent contact between material, equipment or persons and the high voltage overhead lines or temporary deenergization and grounding or temporary relocation or raising of the high voltage overhead lines.
B. The person or business entity responsible for performing the work in the vicinity of the high voltage overhead lines shall pay any actual expenses of the public utility operating high voltage overhead lines in providing arrangements for clearances, except in instances where the public utility operating high voltage overhead lines has installed lines within ten feet of an existing fixture or structure after the fixture or structure has been in place at the permanent location. The public utility is not required to provide the arrangements for clearances until an agreement for payment has been made.
C. The public utility shall commence construction for temporary clearances within five working days of an agreement for payment, if required, or from the date of the request of the person responsible for the work. Once initiated, the clearance work will continue without interruption to completion.
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.