Code · Wisconsin · Chapter 293 — Nonferrous metallic mining

293.95 Review.

428 words·~2 min read·/wi/chapter-293/293-95-2

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

293.95 Review.
(1)Limits on contested case hearings. No person is entitled to a contested case hearing on a decision by the department on an exploration license or relating to bulk sampling. No person is entitled to a contested case hearing on a decision by the department on a mining or prospecting permit application or any other approval, except as provided in subs.
(2)and
(3).
(2)Contested case hearings; after initial mining or prospecting permit decision or decision on amended plan.
(a)Entitlement.
1. A person is entitled to a contested case hearing on a decision by the department related to a mining or prospecting permit for a proposed mining operation, including a decision related to the environmental impact statement for the proposed mining or prospecting operation, or on any decision that is related to an approval associated with the proposed mining or prospecting operation and that is issued no later than the day on which the department issues its decision on the application for the mining or prospecting permit, only if the person is entitled to a contested case hearing on the decision under s. 227.42 and the person requests the hearing within 30 days after the department issues the decision to approve or deny the application for the mining or prospecting permit.
2. A person is entitled to a contested case hearing on a decision by the department related to an amended mining plan, reclamation plan, or mining waste site feasibility study and plan of operation or to any amendment to an approval associated with the amended mining plan, reclamation plan, or mining waste site feasibility study and plan of operation only if the person is entitled to a contested case hearing on the decision under s. 227.42 and the person requests the hearing within 60 days after the department issues the decision to approve or deny the amended mining plan, reclamation plan, or mining waste site feasibility study and plan of operation.
3. All issues raised by all persons requesting a contested case hearing in accordance with subd. 1. or 2. in connection with the same mining or prospecting operation shall be considered in one contested case hearing.
(b)Deadline for decision. The hearing examiner presiding over a contested case hearing under this subsection shall issue a final decision on the case no more than 270 days after the department issues the decision to grant or deny the mining or prospecting permit or to approve or deny the amended mining plan, reclamation plan, or mining waste site feasibility study and plan of operation.
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.