101.15 Mines, tunnels, quarries and pits.
308 words·~1 min read·
/wi/chapter-101/101-15A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
101.15 Mines, tunnels, quarries and pits.
(1)If any shaft or workings of a mine, or any tunnel, trench, caisson, quarry, or gravel or sand pit is being operated or used in violation of the safety orders of the department applicable thereto, the owner or operator upon receiving notice of such violation from the department shall immediately cease such operation or use. The operation or use of such shaft or workings of a mine, or of such tunnel, trench, caisson, quarry or gravel or sand pit, shall not be resumed until such safety orders have been complied with.
(a)For the purpose of this section:
1. “Excavation” or “workings” means any or all parts of a mine excavated or being excavated, including shafts, tunnels, drifts, cross cuts, raises, winzes, stopes and all other working places in a mine.
2. “Mineral” means a product recognized by standard authorities as mineral, whether metalliferous or nonmetalliferous.
3. “Shaft” means an opening made for mining minerals, for hoisting and lowering persons or material, or for ventilating underground workings.
(b)No excavation of a shaft may be commenced unless a permit is first issued therefor by the department. Permits for such excavation shall be issued upon fee payment and application filed with the department, if the department is satisfied that the shaft or the excavation and workings will be in compliance with the safety orders adopted by the department and applicable thereto. Application shall be made upon forms prescribed by the department and shall be furnished upon request.
(c)Paragraph
(b)does not apply to shafts which will be less than 50 feet in depth wherein persons are not employed, or which are not equipped with power driven hoists used for hoisting persons in and out of the shafts, or which are not covered with a flammable building.
(d)The department may: