(1)A net metering system used by a customer-generator shall include, at the customer-generator's own expense, all equipment necessary to meet applicable safety, power quality, and interconnection requirements established by the national electrical code, national electrical safety code, the institute of electrical and electronics engineers, and underwriters laboratories.
(2)The commission, in the case of an electrical company, or the appropriate governing body, in the case of other electric utilities, after appropriate notice and opportunity for comment, may adopt by regulation additional safety, power quality, and interconnection requirements for customer-generators, including limitations on the number of customer-generators and total capacity of net metering systems that may be interconnected to any distribution feeder line, circuit, or network that the commission or governing body determines are necessary to protect public safety and system reliability.
(3)An electric utility may not require a customer-generator whose net metering system meets the standards in subsections
(1)and
(2)of this section to comply with additional safety or performance standards, perform or pay for additional tests, or purchase additional liability insurance. However, an electric utility shall not be liable directly or indirectly for permitting or continuing to allow an attachment of a net metering system, or for the acts or omissions of the customer-generator that cause loss or injury, including death, to any third party.
(4)Except when required under the federal public utility regulatory policies act, an electric utility may not establish compensation arrangements or interconnection requirements, other than those permitted in this chapter, for a customer-generator that would have the effect of prohibiting or restricting the ability of a customer-generator to generate or store electricity for consumption on its premises.
[ 2019 c 235 s 4 ; 2006 c 201 s 4 ; 2000 c 158 s 3 ; 1998 c 318 s 5 .]
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.