Code · Washington · Title 60 — Liens · Chapter 60.28

RCW 60.28.021

312 words·~1 min read·/wa/title-60/chapter-60-28/60-28-021·

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

After the expiration of the forty-five day period for giving notice of lien provided in RCW 60.28.011 (2), and after receipt of the certificates of the department of revenue, the employment security department, and the department of labor and industries, and the public body is satisfied that the taxes certified as due or to become due by the department of revenue, the employment security department, and the department of labor and industries are discharged, and the claims of material suppliers and laborers who have filed their claims, together with a sum sufficient to defray the cost of foreclosing the liens of such claims, and to pay attorneys' fees, have been paid, the public body may withhold from the remaining retained amounts for claims the public body may have against the contractor and shall pay the balance, if any, to the contractor the fund retained by it or release to the contractor the securities and bonds held in escrow.
If such taxes have not been discharged or the claims, expenses, and fees have not been paid, the public body shall either retain in its fund, or in an interest bearing account, or retain in escrow, at the option of the contractor, an amount equal to such unpaid taxes and unpaid claims together with a sum sufficient to defray the costs and attorney fees incurred in foreclosing the lien of such claims, and shall pay, or release from escrow, the remainder to the contractor.
[ 2009 c 432 s 6 ; 2007 c 218 s 94 ; 1992 c 223 s 3 .]
Notes:
Report — 2009 c 432: See RCW 18.27.800 .
Intent — Finding — 2007 c 218: See note following RCW 41.08.020 .
Effective date — 1992 c 223: See note following RCW 39.76.011 .
Waiver of rights, construction — Application — 1992 c 223: See RCW 39.04.900 and 39.04.901 .
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.