RCW 43.52.560
131 words·~1 min read·
/wa/title-43/chapter-43-52/43-52-560·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
Except as provided otherwise in this chapter, a joint operating agency shall purchase any item or items of materials, equipment, or supplies, the estimated cost of which is more than $30,000 exclusive of sales tax, or order work for construction of generating projects and associated facilities, the estimated cost of which is more than $150,000 exclusive of sales tax if more than a single craft or trade is involved, or $75,500 exclusive of sales tax if only a single craft or trade is involved, by contract in accordance with RCW 54.04.070 and 54.04.080 , which require sealed bids for contracts.
[ 2025 c 62 s 1 ; 2015 c 73 s 1 ; 2004 c 189 s 1 ; 1998 c 245 s 69 ; 1987 c 376 s 1 .]