The committee shall:
(1)Certify, or renew certification for, public bodies to use design-build or general contractor/construction manager contracting procedures, or both;
(2)Review and approve the use of the design-build or general contractor/construction manager contracting procedures on a project by project basis for public bodies that are not certified under RCW 39.10.270 ;
(3)Review and approve the use of alternative subcontractor selection under RCW 39.10.385 on a project-by-project basis for public bodies that are not certified under RCW 39.10.270 , which review and approval may be concurrent with project approval; and
(4)Review and approve not more than two design-build demonstration projects that include procurement of operations and maintenance services for a period longer than three years.
[ 2021 c 230 s 5 ; 2019 c 212 s 2 ; 2013 c 222 s 5 ; 2009 c 75 s 2 ; 2007 c 494 s 105 .]