Code of Virginia § 45.2-1302. Examination of dams and mine refuse piles; potentially hazardous conditions; plans to be submitted by licensed operators.

327 words·~1 min read·/va/title-45-2/chapter-13/45-2-1302

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

A. Every water-retaining or silt-retaining dam or mine refuse pile shall be examined daily for visible structural weakness, volume overload, and other hazards by a qualified person designated by the licensed operator. When rising water and silt reaches 80 percent by volume of the safe design capacity of the dam or pile, such examination shall be made more often as required by the Director or his designated agent. Frequent examinations shall be made during periods of rainfall that could create flooding conditions.
B. When a potentially hazardous condition exists, the operator shall initiate procedures to:
1. Remove all persons from the area that can reasonably be expected to be affected by such potentially hazardous condition;
2. Eliminate such potentially hazardous condition; and
3. Notify the Director.
C. Records of the inspections required by subsection A shall be kept and certified by the licensed operator or his agent. Such records shall be kept on the surface at the office or designated station of the mine.
D. The licensed operator of each mineral mine on which a water-retaining or silt-retaining dam is located shall adopt a plan for carrying out the requirements of subsections A and B. The plan shall be submitted for approval to the Director and shall include:
1. A schedule and procedures for the inspection of the retaining dam by a qualified person;
2. Procedures for evaluating any potentially hazardous condition;
3. Procedures for removing all persons from the area that may reasonably be expected to be affected by such potentially hazardous condition;
4. Procedures for eliminating such potentially hazardous condition;
5. Procedures for notifying the Director; and
6. Any additional information that may be required by the Director.
E. Before making any change or modification in the plan approved in accordance with subsection D, the licensed operator shall obtain approval of such change or modification from the Director.
1997, c. 390 , § 45.1-225.2; 1998, c. 695 ; 2021, Sp. Sess. I, c. 387 .
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.