63G-6a-802.7. Extension of a contract without engaging in a standard procurement process.

334 words·~2 min read·/ut/title-63g/chapter-6a/63g-6a-802-7·

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

Effective 5/12/2020
63G-6a-802.7. Extension of a contract without engaging in a standard procurement process.
A procurement official may extend an existing contract without engaging in a standard procurement process:
(1)for a period of time not to exceed 120 days, if:
(a)an extension of the contract is necessary to:
(i)avoid a lapse in a critical government service; or
(ii)to mitigate a circumstance that is likely to have a negative impact on public health, safety, welfare, or property; and
(A)the procurement unit is engaged in a standard procurement process for a procurement item that is the subject of the contract being extended; and
(B)the standard procurement process is delayed due to an unintentional error;
(ii)a change in an industry standard requires one or more significant changes to specifications for the procurement item; or
(iii)an extension is necessary:
(A)to prevent the loss of federal funds;
(B)to mitigate the effects of a delay of a state or federal appropriation;
(C)to enable the procurement unit to continue to receive a procurement item during a delay in the implementation of a contract awarded pursuant to a procurement that has already been conducted; or
(D)to enable the procurement unit to continue to receive a procurement item during a period of time during which negotiations with a vendor under a new contract for the procurement item are being conducted;
(2)for the period of a protest, appeal, or court action, if the protest, appeal, or court action is the reason for delaying the award of a new contract; or
(3)for a period of time exceeding 120 days, if, after consulting with the attorney general or the procurement unit's attorney, the procurement official determines in writing that the contract extension does not violate state or federal antitrust laws and is consistent with the purpose of ensuring the fair and equitable treatment of all persons who deal with the procurement system.
Amended by Chapter 257 , 2020 General Session
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.