54-26-802. Commission review.
The commission shall:
(1)conduct a review of this chapter before October 31, 2027, and every three years thereafter;
(2)conduct an investigation with stakeholder input and public comment and prepare a report that includes:
(a)data on program participation;
(b)analysis of impacts on electrical rates;
(c)assessment of transmission system reliability; and
(d)recommendations regarding whether to:
(i)extend the program;
(ii)modify program requirements; or
(iii)allow the program to close to new participants; and
(3)provide the report described in Subsection
(2)and any recommendations to the Public Utilities, Energy, and Technology Interim Committee.
Enacted by Chapter 318 , 2025 General Session