§ 3733. Limitation on use of funds until certain permits obtained

326 words·~1 min read·/usc/title-50/section-3733

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

(a)In general The Secretary of Defense shall seek to obtain all the permits required to complete each phase of construction of a project under the Program in a state of the former Soviet Union before obligating more than 40 percent of the total costs of that phase of the project.
(b)Use of funds for new construction projects Except as provided in subsection (c), with respect to a new construction project to be carried out by the Program, not more than 40 percent of the total costs of the project may be obligated from Cooperative Threat Reduction funds for any fiscal year until the Secretary—
(1)determines the number and type of permits that may be required for the lifetime of the project in the proposed location or locations of the project; and
(2)obtains from the state in which the project is to be located any permits that may be required to begin construction.
(c)Exception to limitations on use of funds The limitation in subsection
(b)on the obligation of funds for a construction project otherwise covered by such subsection shall not apply with respect to the obligation of funds for a particular project if the Secretary—
(1)determines that it is necessary in the national interest to obligate funds for such project; and
(2)submits to the congressional defense committees a notification of the intent to obligate funds for such project, together with a complete discussion of the justification for doing so.
(d)Definitions In this section, with respect to a project under the Program:
(1)The term “new construction project” means a construction project for which no funds have been obligated or expended as of November 24, 2003.
(2)The term “permit” means any local or national permit for development, general construction, environmental, land use, or other purposes that is required for purposes of major construction.
(Pub. L. 113–291, div. A, title XIII, § 1333, Dec. 19, 2014, 128 Stat. 3602.)
Connections3 cite this · traces to 1
1 reference not yet in our index
  • 128 Stat. 3602
Citation graph
cites case law
§ 3733
Limitation on use of funds until certain permits obtained
Pub. L.×1
Stat. Comp.×1
U.S.C.×1
Stat.128 Stat. 3602
Cites 2Cited by 3 across 3 sources
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.