§ 7104. Contractor’s right of appeal from decision by contracting officer

298 words·~1 min read·/usc/title-41/section-7104

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

(a)Appeal to Agency Board.— A contractor, within 90 days from the date of receipt of a contracting officer’s decision under section 7103 of this title, may appeal the decision to an agency board as provided in section 7105 of this title.
(b)Bringing an Action De Novo in Federal Court.—
(1)In general.— Except as provided in paragraph (2), and in lieu of appealing the decision of a contracting officer under section 7103 of this title to an agency board, a contractor may bring an action directly on the claim in the United States Court of Federal Claims, notwithstanding any contract provision, regulation, or rule of law to the contrary.
(2)Tennessee valley authority.— In the case of an action against the Tennessee Valley Authority, the contractor may only bring an action directly on the claim in a district court of the United States pursuant to section 1337 of title 28, notwithstanding any contract provision, regulation, or rule of law to the contrary.
(3)Time for filing.— A contractor shall file any action under paragraph
(1)or
(2)within 12 months from the date of receipt of a contracting officer’s decision under section 7103 of this title.
(4)De novo.— An action under paragraph
(1)or
(2)shall proceed de novo in accordance with the rules of the appropriate court.
(Pub. L. 111–350, § 3, Jan. 4, 2011, 124 Stat. 3820.)
In subsection (a), the words “of contract appeals” are omitted as unnecessary because of the definition of “agency board” in section 7101 of the revised title.
In subsection (b)(1), the words “United States Court of Federal Claims” are substituted for “United States Claims Court” because of section 902(b)(1) of the Federal Courts Administration Act of 1992 (Pub. L. 102–572, 106 Stat. 4516, 28 U.S.C. 171 note).
Connections18 cite this · traces to 4
4 references not yet in our index
  • Pub. L. 111–350, § 3
  • 124 Stat. 3820
  • Pub. L. 102–572
  • 106 Stat. 4516
Citation graph
cites case law
§ 7104
Contractor’s right of appeal from decision by contracting officer
U.S.C.×17
Fed. Reg.×1
Pub. L.Pub. L. 111–350, § 3
Stat.124 Stat. 3820
Pub. L.Pub. L. 102–572
Stat.106 Stat. 4516
Cites 8Cited by 18 across 2 sources
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.