Tap any paragraph to write a margin note. Your notes collect in the Desk below the text and file under cases with @. The side-by-side margin rail opens on a larger screen.

Code · U.S. Code · Title 41 - PUBLIC CONTRACTS · CHAPTER 39— SPECIFIC TYPES OF CONTRACTS · § 3905

§ 3905. Cost contracts

271 words·~1 min read·/usc/title-41/section-3905

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

(a)Cost-Plus-A-Percentage-Of-Cost Contracts Disallowed.— The cost-plus-a-percentage-of-cost system of contracting shall not be used.
(b)Cost-Plus-A-Fixed-Fee Contracts.—
(1)In general.— Except as provided in paragraphs
(2)and (3), the fee in a cost-plus-a-fixed-fee contract shall not exceed 10 percent of the estimated cost of the contract, not including the fee, as determined by the agency head at the time of entering into the contract.
(2)Experimental, developmental, or research work.— The fee in a cost-plus-a-fixed-fee contract for experimental, developmental, or research work shall not exceed 15 percent of the estimated cost of the contract, not including the fee.
(3)Architectural or engineering services.— The fee in a cost-plus-a-fixed-fee contract for architectural or engineering services relating to any public works or utility project may include the contractor’s costs and shall not exceed 6 percent of the estimated cost, not including the fee, as determined by the agency head at the time of entering into the contract, of the project to which the fee applies.
(c)Notification.— All cost and cost-plus-a-fixed-fee contracts shall provide for advance notification by the contractor to the procuring agency of any subcontract on a cost-plus-a-fixed-fee basis and of any fixed-price subcontract or purchase order which exceeds in dollar amount either the simplified acquisition threshold or 5 percent of the total estimated cost of the prime contract.
(d)Right To Audit.— A procuring agency, through any authorized representative thereof, has the right to inspect the plans and to audit the books and records of a prime contractor or subcontractor engaged in the performance of a cost or cost-plus-a-fixed-fee contract.
(Pub. L. 111–350, § 3, Jan. 4, 2011, 124 Stat. 3776.)
Connections19 cite this
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.