§ 426e–3. Coastal storm damage reduction contracts
110 words·~1 min read·
/usc/title-33/section-426e-3A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
For any project for coastal storm damage reduction, the Secretary may seek input from a non-Federal interest for a project that may be affected by the timing of the coastal storm damage reduction activities under the project, in order to minimize, to the maximum extent practicable, any negative effects resulting from the timing of those activities. ( Pub. L. 116–260, div. AA, title I, § 140 , Dec. 27, 2020 , 134 Stat. 2652 .)