§ 306. Contracting methods in capital construction
409 words·~2 min read·
/usc/title-22/section-306A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
(a)Delivery Unless the Secretary of State notifies the appropriate congressional committees that the use of the design-build project delivery method would not be appropriate, the Secretary shall make use of such method at United States diplomatic posts that have not yet received design or capital construction contracts as of December 27, 2021.
(b)Notification Before executing a contract for a delivery method other than design-build in accordance with subsection (a), the Secretary of State shall notify the appropriate congressional committees in writing of the decision, including the reasons therefor. The notification required by this subsection may be included in any other report regarding a new United States diplomatic post that is required to be submitted to the appropriate congressional committees.
(c)Performance evaluation Not later than 180 days after December 27, 2021, the Secretary of State shall report to the appropriate congressional committees regarding performance evaluation measures in accordance with GAO’s “Standards for Internal Control in the Federal Government” that will be applicable to design and construction, lifecycle cost, and building maintenance programs of the Bureau of Overseas Building Operations of the Department.
(Pub. L. 117–81, div. E, title LII, § 5211, Dec. 27, 2021, 135 Stat. 2358.)
Connections7 cite this · traces to 3
Cited by 7 sections · top 5
public-private-law
statute-compilations
Traces to 3 documents
2 references not yet in our index
- 135 Stat. 2358
- 135 Stat. 2359
Citation graph
cites case law
§ 306
Contracting methods in capital construction
Pub. L.×2
Stat. Comp.×2
Stat.×2
U.S.C.×1
Stat.135 Stat. 2358
Stat.135 Stat. 2359
Cites 5Cited by 7 across 4 sources