§ 824i. Interconnection authority

738 words·~3 min read·/usc/title-16/section-824i

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

(a)Powers of Commission; application by State regulatory authority
(1)Upon application of any electric utility, Federal power marketing agency, geothermal power producer (including a producer which is not an electric utility), qualifying cogenerator, or qualifying small power producer, the Commission may issue an order requiring—
(A)the physical connection of any cogeneration facility, any small power production facility, or the transmission facilities of any electric utility, with the facilities of such applicant,
(B)such action as may be necessary to make effective any physical connection described in subparagraph (A), which physical connection is ineffective for any reason, such as inadequate size, poor maintenance, or physical unreliability,
(C)such sale or exchange of electric energy or other coordination, as may be necessary to carry out the purposes of any order under subparagraph
(A)or (B), or
(D)such increase in transmission capacity as may be necessary to carry out the purposes of any order under subparagraph
(A)or (B).
(2)Any State regulatory authority may apply to the Commission for an order for any action referred to in subparagraph (A), (B), (C), or
(D)of paragraph (1). No such order may be issued by the Commission with respect to a Federal power marketing agency upon application of a State regulatory authority.
(b)Notice, hearing and determination by Commission Upon receipt of an application under subsection (a), the Commission shall—
(1)issue notice to each affected State regulatory authority, each affected electric utility, each affected Federal power marketing agency, each affected owner or operator of a cogeneration facility or of a small power production facility, and to the public.1
(2)afford an opportunity for an evidentiary hearing, and
(3)make a determination with respect to the matters referred to in subsection (c).
(c)Necessary findings No order may be issued by the Commission under subsection
(a)unless the Commission determines that such order—
(1)is in the public interest,
(2)would—
(A)encourage overall conservation of energy or capital,
(B)optimize the efficiency of use of facilities and resources, or
(C)improve the reliability of any electric utility system or Federal power marketing agency to which the order applies, and
(3)meets the requirements of section 824k of this title.
(d)Motion of Commission The Commission may, on its own motion, after compliance with the requirements of paragraphs
(1)and
(2)of subsection (b), issue an order requiring any action described in subsection (a)(1) if the Commission determines that such order meets the requirements of subsection (c). No such order may be issued upon the Commission’s own motion with respect to a Federal power marketing agency.
(e)Definitions
(1)As used in this section, the term “facilities” means only facilities used for the generation or transmission of electric energy.
(2)With respect to an order issued pursuant to an application of a qualifying cogenerator or qualifying small power producer under subsection (a)(1), the term “facilities of such applicant” means the qualifying cogeneration facilities or qualifying small power production facilities of the applicant, as specified in the application. With respect to an order issued pursuant to an application under subsection (a)(2), the term “facilities of such applicant” means the qualifying cogeneration facilities, qualifying small power production facilities, or the transmission facilities of an electric utility, as specified in the application. With respect to an order issued by the Commission on its own motion under subsection (d), such term means the qualifying cogeneration facilities, qualifying small power production facilities, or the transmission facilities of an electric utility, as specified in the proposed order.
(June 10, 1920, ch. 285, pt. II, § 210, as added Pub. L. 95–617, title II, § 202, Nov. 9, 1978, 92 Stat. 3135; amended Pub. L. 96–294, title VI, § 643(a)(2), June 30, 1980, 94 Stat. 770.)
Connections33 cite this · traces to 2
8 references not yet in our index
  • 1
  • June 10, 1920, ch. 285
  • Pub. L. 95–617, title II, § 202
  • 92 Stat. 3135
  • Pub. L. 96–294, title VI, § 643(a)(2)
  • 94 Stat. 770
  • Pub. L. 96–294
  • section 8(d) of Pub. L. 99–495
Citation graph
cites case law
§ 824i
Interconnection authority
Fed. Reg.×20
U.S.C.×8
C.F.R.×2
Stat.×2
Stat. Comp.×1
Cite1
ActJune 10, 1920, ch. 285
Pub. L.Pub. L. 95–617, title II, § 202
Stat.92 Stat. 3135
Pub. L.Pub. L. 96–294, title VI, § 643(a)(2)
Cites 10 · showing 7Cited by 33 across 5 sources
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.