§ 6312. Independent acquisition project reviews of capital assets acquisition projects

339 words·~2 min read·/usc/title-10/section-6312

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

(a)Reviews.— The appropriate head shall ensure that an independent entity conducts reviews of each capital assets acquisition project as the project moves toward the approval of each of critical decision 0, critical decision 1, and critical decision 2 in the acquisition process.
(b)Pre-critical Decision 1 Reviews.— In addition to any other matters, with respect to each review of a capital assets acquisition project under subsection
(a)that has not reached critical decision 1 approval in the acquisition process, such review shall include—
(1)a review using best practices of the analysis of alternatives for the project; and
(2)identification of any deficiencies in such analysis of alternatives for the appropriate head to address.
(c)Independent Entities.— The appropriate head shall ensure that each review of a capital assets acquisition project under subsection
(a)is conducted by an independent entity with the appropriate expertise with respect to the project and the stage in the acquisition process of the project.
(d)Definitions.— In this section:
(1)The term “acquisition process” means the acquisition process for a project, as defined in Department of Energy Order 413.3B (relating to project management and project management for the acquisition of capital assets), or a successor order.
(2)The term “appropriate head” means—
(A)the Administrator, with respect to capital assets acquisition projects of the Administration; and
(B)the Assistant Secretary of Energy for Environmental Management, with respect to capital assets acquisition projects of the Office of Environmental Management.
(3)The term “capital assets acquisition project” means a project—
(A)the total project cost of which is more than $500,000,000; and
(B)that is covered by Department of Energy Order 413.3B, or a successor order, for the acquisition of capital assets for atomic energy defense activities.
(Added Pub. L. 119–60, div. C, title XXXI, § 3111(a), Dec. 18, 2025, 139 Stat. 1439.)
Connections4 off-index
4 references not yet in our index
  • Pub. L. 119–60, div. C, title XXXI, § 3111(a)
  • 139 Stat. 1439
  • section 2773 of Title 50
  • Pub. L. 119–60, § 3111(b)(1)
Citation graph
cites case law
§ 6312
Independent acquisition project reviews of capital assets acquisition projects
Pub. L.Pub. L. 119–60, div. C, title XXXI, § 3111(a)
Stat.139 Stat. 1439
Citesection 2773 of Title 50
Pub. L.Pub. L. 119–60, § 3111(b)(1)
Cites 4Cited by 0 across 0 sources
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.