§ 4374. Unit cost reports: determinations by service acquisition executive and secretary concerned of breach of significant cost growth threshold or critical cost growth threshold; reports to Congress
842 words·~4 min read·
/usc/title-10/section-4374A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
(a)Determination of Breach by Service Acquisition Executive.— When a unit cost report is submitted to the service acquisition executive designated by the Secretary concerned under this chapter with respect to a major defense acquisition program or any designated major subprogram under the program, the service acquisition executive shall determine whether the current program acquisition unit cost for the program or subprogram has increased by a percentage equal to or greater than the significant cost growth threshold, or the critical cost growth threshold, for the program or subprogram.
(b)Additional Determination by Service Acquisition Executive When Program or Subprogram Is a Procurement Program.— When a unit cost report is submitted to the service acquisition executive designated by the Secretary concerned under this chapter with respect to a major defense acquisition program or any designated major subprogram under the program that is a procurement program, the service acquisition executive, in addition to the determination under subsection (a), shall determine whether the procurement unit cost for the program or subprogram has increased by a percentage equal to or greater than the significant cost growth threshold, or the critical cost growth threshold, for the program or subprogram.
(c)Determination of Breach by Secretary Concerned; Notification to Congress.—
(1)In general.— If, based upon the service acquisition executive’s determination, the Secretary concerned determines that the current program acquisition unit cost has increased by a percentage equal to or greater than the significant cost growth threshold or critical cost growth threshold or that the procurement unit cost has increased by a percentage equal to or greater than the significant cost growth threshold or critical cost growth threshold, the Secretary shall notify Congress in writing of such determination and of the increase with respect to the program or subprogram concerned.
(2)Time for submission of notification to congress.— In the case of a determination based on a quarterly report submitted in accordance with section 4372 of this title, the Secretary shall submit the notification to Congress within 45 days after the end of the quarter. In the case of a determination based on a report submitted in accordance with section 4373 of this title, the Secretary shall submit the notification to Congress within 45 days after the date of that report.
(3)Inclusion of date of determination.— The Secretary shall include in the notification the date on which the determination was made.
(Added and amended Pub. L. 116–283, div. A, title XVIII, § 1850(a), (g), Jan. 1, 2021, 134 Stat. 4265, 4267.)
Connections19 cite this · traces to 5
Cited by 19 sections · top 8
public-private-law
U.S. Code
- § 3501Multiyear contracts: acquisition of property
- § 4214Baseline description
- § 4376Breach of critical cost growth threshold: reassessment of program; presumption of program termination
- § 4375Breach of significant cost growth threshold or critical cost growth threshold: required action
- § 4062Defense Acquisition Challenge Program
statute-compilations
Traces to 5 documents
U.S. Code
- Unit cost reports: quarterly report from program manager to service acquisition executive§ 4372
- Unit cost reports: immediate report from program manager to service acquisition executive upon breach of significant cost growth threshold§ 4373
- Repealed. Pub. L. 116–283, div. A, title XVIII, § 1850(l), Jan. 1, 2021, 134 Stat. 4271]§ 2433
- Defense acquisition system; element of the defense acquisition system§ 3001
23 references not yet in our index
- 134 Stat. 4265
- Pub. L. 97–252, title XI, § 1107(a)(1)
- 96 Stat. 741
- Pub. L. 98–525, title XII, § 1242(b)(4)
- 98 Stat. 2608
- Pub. L. 99–145, title XIII, § 1303(a)(2)
- 99 Stat. 738
- Pub. L. 99–433, title I, § 101(a)(5)
- 100 Stat. 995
- Pub. L. 100–180, div. A, title XIII, § 1314(a)(1)
- 101 Stat. 1175
- Pub. L. 101–189, div. A, title VIII, § 811(a)(4)
- 103 Stat. 1491
- Pub. L. 102–484, div. A, title VIII, § 817(d)(4)
- 106 Stat. 2457
- Pub. L. 103–355, title III
- 108 Stat. 3328
- Pub. L. 105–85, div. A, title VIII, § 833(c)
- 111 Stat. 1843
- Pub. L. 109–163, div. A, title VIII, § 802(b)(2)
- 119 Stat. 3368
- Pub. L. 110–417
- 122 Stat. 4523
Citation graph
cites case law
§ 4374
Unit cost reports: determinations by service acquisition executive and secretary concerned of breach of significant cost growth threshold or critical cost growth threshold; reports to Congress
U.S.C.×16
Pub. L.×1
Stat. Comp.×1
Stat.×1
Stat.134 Stat. 4265
Pub. L.Pub. L. 97–252, title XI, § 1107(a)(1)
Stat.96 Stat. 741
Pub. L.Pub. L. 98–525, title XII, § 1242(b)(4)
Stat.98 Stat. 2608
Cites 28 · showing 10Cited by 19 across 4 sources