§ 61.173. Compliance provisions.
129 words·~1 min read·
/us/cfr/t40/s§ 61.173·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
(a)The owner or operator of each copper converter to which § 61.172(b)-(f) applies shall demonstrate compliance with the requirements of § 61.172(b)(1) as follows:
(1)The owner or operator of each existing copper converter shall install a secondary hood system to meet the requirements of § 61.172(b)(1) no later than 90 days after the effective date, unless a waiver of compliance has been approved by the Administrator in accordance with § 61.11.
(2)The owner or operator of each new copper converter shall install a secondary hood system to meet the requirements of § 61.172(b)(1) prior to the initial startup of the converter, except that if startup occurs prior to the effective date, the owner or operator shall meet the requirements of § 61.172(b)(1) on the effective date.