§ 61.08. Approval of construction or modification.

273 words·~1 min read·/us/cfr/t40/s§ 61.08·

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

(a)The Administrator will notify the owner or operator of approval or intention to deny approval of construction or modification within 60 days after receipt of sufficient information to evaluate an application under § 61.07.
(b)If the Administrator determines that a stationary source for which an application under § 61.07 was submitted will not cause emissions in violation of a standard if properly operated, the Administrator will approve the construction or modification.
(c)Before denying any application for approval of construction or modification, the Administrator will notify the applicant of the Administrator's intention to issue the denial together with—
(1)Notice of the information and findings on which the intended denial is based; and
(2)Notice of opportunity for the applicant to present, within such time limit as the Administrator shall specify, additional information or arguments to the Administrator before final action on the application.
(d)A final determination to deny any application for approval will be in writing and will specify the grounds on which the denial is based. The final determination will be made within 60 days of presentation of additional information or arguments, or 60 days after the final date specified for presentation if no presentation is made.
(e)Neither the submission of an application for approval nor the Administrator's approval of construction or modification shall—
(1)Relieve an owner or operator of legal responsibility for compliance with any applicable provisions of this part or of any other applicable Federal, State, or local requirement; or
(2)Prevent the Administrator from implementing or enforcing this part or taking any other action under the Act. [50 FR 46291, Nov. 7, 1985]
Connections2 cite this
Citation graph
cites case law
§ 61.08
Approval of construction or modification.
Fed. Reg.×2
Cites 0Cited by 2 across 1 source
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.