§ 60.4925. When must I submit a title V permit application for my new SSI unit?
356 words·~2 min read·
/us/cfr/t40/s§ 60.4925·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
(a)If your new SSI unit subject to this subpart is not subject to an earlier permit application deadline, a complete Title V permit application must be submitted on or before one of the dates specified in paragraph (a)(1) or (a)(2) of this section. (See section 503(c) of the Clean Air Act and 40 CFR 70.5(a)(1)(i) and 40 CFR 71.5(a)(1)(i)).
(1)For a SSI unit that commenced operation as a new SSI unit as of March 21, 2011, then a complete title V permit application must be submitted not later than March 21, 2012.
(2)For a SSI unit that does not commence operation as a new SSI unit until after March 21, 2011, then a complete title V permit application must be submitted not later than 12 months after the date the unit commences operation as a new source.
(b)If your new SSI unit subject to this subpart is subject to title V as a result of some triggering requirement(s) other than this subpart (for example, a unit subject to this subpart may be a major source or part of a major source), then your unit may be required to apply for a title V permit prior to the deadlines specified in paragraph
(a)of this section. If more than one requirement triggers a source's obligation to apply for a title V permit, the 12-month timeframe for filing a title V permit application is triggered by the requirement that first causes the source to be subject to title V. (See section 503(c) of the Clean Air Act and 40 CFR 70.3(a) and (b), 40 CFR 70.5(a)(1)(i), 40 CFR 71.3(a) and (b), and 40 CFR 71.5(a)(1)(i).)
(c)A “complete” title V permit application is one that has been determined or deemed complete by the relevant permitting authority under section 503(d) of the Clean Air Act and 40 CFR 70.5(a)(2) or 40 CFR 71.5(a)(2). You must submit a complete permit application by the relevant application deadline in order to operate after this date in compliance with Federal law. (See sections 503(d) and 502(a) of the Clean Air Act and 40 CFR 70.7(b) and 40 CFR 71.7(b).)
Connections8 off-index
8 references not yet in our index
- 40 CFR 70.5(a)(1)(i)
- 40 CFR 71.5(a)(1)(i)
- 40 CFR 70.3(a)
- 40 CFR 71.3(a)
- 40 CFR 70.5(a)(2)
- 40 CFR 71.5(a)(2)
- 40 CFR 70.7(b)
- 40 CFR 71.7(b)
Citation graph
cites case law
§ 60.4925
When must I submit a title V permit application for my new SSI unit?
Cite40 CFR 70.5(a)(1)(i)
Cite40 CFR 71.5(a)(1)(i)
Cite40 CFR 70.3(a)
Cite40 CFR 71.3(a)
Cite40 CFR 70.5(a)(2)
Cites 8 · showing 5Cited by 0 across 0 sources