§ 60.1935. What equations must I use?

645 words·~3 min read·/us/cfr/t40/s§ 60.1935·

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

(a)Concentration correction to 7 percent oxygen. Correct any pollutant concentration to 7 percent oxygen using equation 1 of this section: Where: C7% = concentration corrected to 7 percent oxygen. Cunc = uncorrected pollutant concentration. CO2 = concentration of oxygen (percent).
(b)Percent reduction in potential mercury emissions. Calculate the percent reduction in potential mercury emissions (%PHg) using equation 2 of this section: Where: %PHg = percent reduction of potential mercury emissions Ei = mercury emission concentration as measured at the air pollution control device inlet, corrected to 7 percent oxygen, dry basis Eo = mercury emission concentration as measured at the air pollution control device outlet, corrected to 7 percent oxygen, dry basis
(c)Percent reduction in potential hydrogen chloride emissions. Calculate the percent reduction in potential hydrogen chloride emissions (%PHC1) using equation 3 of this section: Where: %PHC1 = percent reduction of the potential hydrogen chloride emissions Ei = hydrogen chloride emission concentration as measured at the air pollution control device inlet, corrected to 7 percent oxygen, dry basis Eo = hydrogen chloride emission concentration as measured at the air pollution control device outlet, corrected to 7 percent oxygen, dry basis
(d)Capacity of a municipal waste combustion unit. For a municipal waste combustion unit that can operate continuously for 24-hour periods, calculate the municipal waste combustion unit capacity based on 24 hours of operation at the maximum charge rate. To determine the maximum charge rate, use one of two methods:
(1)For municipal waste combustion units with a design based on heat input capacity, calculate the maximum charging rate based on the maximum heat input capacity and one of two heating values:
(i)If your municipal waste combustion unit combusts refuse-derived fuel, use a heating value of 12,800 kilojoules per kilogram (5,500 British thermal units per pound).
(ii)If your municipal waste combustion unit combusts municipal solid waste, use a heating value of 10,500 kilojoules per kilogram (4,500 British thermal units per pound).
(2)For municipal waste combustion units with a design not based on heat input capacity, use the maximum designed charging rate.
(e)Capacity of a batch municipal waste combustion unit. Calculate the capacity of a batch municipal waste combustion unit as the maximum design amount of municipal solid waste they can charge per batch multiplied by the maximum number of batches they can process in 24 hours. Calculate the maximum number of batches by dividing 24 by the number of hours needed to process one batch. Retain fractional batches in the calculation. For example, if one batch requires 16 hours, the municipal waste combustion unit can combust 24/16, or 1.5 batches, in 24 hours.
(f)Quarterly carbon usage. If you use activated carbon to comply with the dioxins/furans or mercury limits, calculate the required quarterly usage of carbon using equation 4 of this section for plant basis or equation 5 of this section for unit basis:
(1)Plant basis. Where: C = required quarterly carbon usage for the plant in kilograms (or pounds). fi = required carbon feed rate for the municipal waste combustion unit in kilograms (or pounds) per hour. That is the average carbon feed rate during the most recent mercury or dioxins/furans stack tests (whichever has a higher feed rate). hi = number of hours the municipal waste combustion unit was in operation during the calendar quarter (hours). n = number of municipal waste combustion units, i, located at your plant.
(2)Unit basis. Where: C = required quarterly carbon usage for the unit in kilograms (or pounds). f = required carbon feed rate for the municipal waste combustion unit in kilograms (or pounds) per hour. That is the average carbon feed rate during the most recent mercury or dioxins/furans stack tests (whichever has a higher feed rate). h = number of hours the municipal waste combustion unit was in operation during the calendar quarter (hours).
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.