§ 60.1215. What emission limits must I meet? By when?
43 words·~1 min read·
/us/cfr/t40/s§ 60.1215·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
You must meet the emission limits specified in tables 1 and 2 of this subpart. You must meet the limits 60 days after your municipal waste combustion unit reaches the maximum load level but no later than 180 days after its initial startup.