Code · CFR · Title 36 — Parks, Forests, and Public Property · Part 14 · § 14.11

§ 14.11. Special use permit for construction.

249 words·~1 min read·/us/cfr/t36/s§ 14.11·

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

(a)Permit requirement. Applicants must apply for and obtain a separate special use permit for construction prior to beginning construction associated with a right-of-way permit.
(b)Application form. The applicant must use the currently approved application form for a special use permit.
(c)Complete application. The NPS will not begin processing an application for a special use permit for construction until the NPS has reviewed the application and determined that it is complete.
(d)Associated right-of-way permit. The NPS will only issue a special use permit for construction simultaneously or after it issues an associated right-of-way permit.
(e)Application information.
(1)The applicant must include all of the information required by the currently approved special use permit application form. This information must include, at a minimum, the following information:
(i)Description of proposed activity.
(ii)Requested location.
(iii)Proposed schedule, including proposed start and end dates, and interim activities.
(iv)List of equipment.
(2)The applicant is encouraged to attach additional pages with information useful in evaluating the permit request, including:
(i)Construction drawings.
(ii)A map showing areas for construction activities, including staging areas and access routes.
(iii)A construction area restoration plan, as applicable.
(3)The NPS may require additional information by written request.
(f)Affidavit. Prior to issuing a special use permit for construction, the NPS may require the applicant to provide an affidavit stating that all other required land rights, water rights, permits, certifications, approvals, and authorizations necessary for a viable project have been secured.
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.