§ 385.13. Projects implemented under additional program authority.
119 words·~1 min read·
/us/cfr/t33/s§ 385.13·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
(a)To expedite implementation of the Plan, the Corps of Engineers and non-Federal sponsors may implement projects under the authority of section 601(c) of WRDA 2000 that are described in the Plan and that will produce a substantial benefit to the restoration, preservation, and protection of the South Florida ecosystem.
(b)Each project implemented under the authority of section 601(c) of WRDA 2000 shall:
(1)In general, follow the process described in § 385.11;
(2)Not be implemented until a Project Implementation Report is prepared and approved in accordance with § 385.26; and
(3)Not exceed a total cost of \$25,000,000.
(c)The total aggregate cost of all projects implemented under the additional program authority shall not exceed \$206,000,000.