§ 157.148. COW system: Evidence for inspections.
102 words·~1 min read·
/us/cfr/t33/s§ 157.148·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
(a)Before the inspections under § 157.140 are conducted by the Coast Guard, the owner or operator of a foreign tank vessel that is to be inspected must submit to the Coast Guard inspector evidence that the COW system has been installed in accordance with the plans accepted under § 157.106.
(b)Before the inspections under § 157.140 are conducted by the Coast Guard, the owner or operator of a tank vessel that is to be inspected must submit to the Coast Guard inspector evidence that the COW piping system has passed a test of 1 1/2 times the design working pressure.