§ 154.1220. Response plan submission requirements.
153 words·~1 min read·
/us/cfr/t33/s§ 154.1220·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
(a)The owner or operator of an MTR facility identified in § 154.1216 as a substantial harm facility, shall prepare and submit to the cognizant COTP a response plan that complies with this subpart and all sections of subpart F of this part, as appropriate, except §§ 154.1015, 154.1016, 154.1017, 154.1028, 154.1045 and 154.1047.
(b)The owner or operator of an MTR facility classified by the COTP under § 154.1216(b) as a significant and substantial harm facility, shall prepare and submit for review and approval of the cognizant COTP a response plan that complies with this subpart and all sections of subpart F of this part, as appropriate, except §§ 154.1015, 154.1016, 154.1017, 154.1028, 154.1045 and 154.1047.
(c)In addition to the requirements in paragraph
(a)of this section, the response plan for a mobile MTR facility must meet the requirements of § 154.1041 subpart F. \[USCG-1999-5149, 65 FR 40825, June 30, 2000\]