§ 150.50. What are the requirements for a facility spill response plan?
110 words·~1 min read·
/us/cfr/t33/s§ 150.50·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
(a)Each deepwater port which meets the applicability requirements of part 154 subpart F of this chapter must have a facility response plan that is approved by the Sector Commander, or MSU Commander, with COTP and OCMI authority.
(b)Each natural gas deepwater port must have a natural gas facility emergency plan that meets part 127, subpart B of this chapter.
(c)The response plan must be submitted to the Sector Commander, or MSU Commander, with COTP and OCMI authority, in writing, not less than 60 days before the deepwater port begins operation. \[USCG-1998-3884, 71 FR 57651, Sept. 29, 2006, as amended by USCG-2013-0397, 78 FR 39181, July 1, 2013\]