§ 817.122. Subsidence control: Public notice.
98 words·~1 min read·
/us/cfr/t30/s§ 817.122·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
At least 6 months prior to mining, or within that period if approved by the regulatory authority, the underground mine operator shall mail a notification to all owners and occupants of surface property and structures above the underground workings. The notification shall include, at a minimum, identification of specific areas in which mining will take place, dates that specific areas will be undermined, and the location or locations where the operator's subsidence control plan may be examined. \[48 FR 24652, June 1, 1983, as amended at 81 FR 93418, Dec. 20, 2016; 82 FR 54999, Nov. 17, 2017\]