§ 816.73. Disposal of excess spoil: Durable rock fills.

314 words·~1 min read·/us/cfr/t30/s§ 816.73·

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

The regulatory authority may approve the alternative method of disposal of excess durable rock spoil by gravity placement in single or multiple lifts, provided the following conditions are met:
(a)Except as provided in this section, the requirements of § 816.71 are met.
(b)The excess spoil consists of at least 80 percent, by volume, durable, nonacid- and nontoxic-forming rock (e.g., sandstone or limestone) that does not slake in water and will not degrade to soil material. Where used, noncemented clay shale, clay spoil, soil or other nondurable excess spoil materials shall be mixed with excess durable rock spoil in a controlled manner such that no more than 20 percent of the fill volume, as determined by tests performed by a registered engineer and approved by the regulatory authority, is not durable rock.
(c)A qualified registered professional engineer certifies that the design will ensure the stability of the fill and meet all other applicable requirements.
(d)The fill is designed to attain a minimum long-term static safety factor of 1.5, and an earthquake safety factor of 1.1.
(e)The underdrain system may be constructed simultaneously with excess spoil placement by the natural segregation of dumped materials, provided the resulting underdrain system is capable of carrying anticipated seepage of water due to rainfall away from the excess spoil fill and from seeps and springs in the foundation of the disposal area and the other requirements for drainage control are met.
(f)Surface water runoff from areas adjacent to and above the fill is not allowed to flow onto the fill and is diverted into stabilized diversion channels designed to meet the requirements of § 816.43 and to safely pass the runoff from a 100-year, 6-hour precipitation event. \[48 FR 32926, July 19, 1983, as amended at 48 FR 44780, Sept. 30, 1983; 81 FR 93392, Dec. 20, 2016; 82 FR 54979, Nov. 17, 2017\]
Connections17 cite this
Citation graph
cites case law
§ 816.73
Disposal of excess spoil: Durable rock fills.
Fed. Reg.×17
Cites 0Cited by 17 across 1 source
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.