§ 816.62. Use of explosives: Preblasting survey.

311 words·~1 min read·/us/cfr/t30/s§ 816.62·

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

(a)At least 30 days before initiation of blasting, the operator shall notify, in writing, all residents or owners of dwellings or other structures located within 1/2 mile of the permit area how to request a preblasting survey.
(b)A resident or owner of a dwelling or structure within 1/2 mile of any part of the permit area may request a preblasting survey. This request shall be made, in writing, directly to the operator or to the regulatory authority, who shall promptly notify the operator. The operator shall promptly conduct a preblasting survey of the dwelling or structure and promptly prepare a written report of the survey. An updated survey of any additions, modifications, or renovations shall be performed by the operator if requested by the resident or owner.
(c)The operator shall determine the condition of the dwelling or structure and shall document any preblasting damage and other physical factors that could reasonably be affected by the blasting. Structures such as pipelines, cables, transmission lines, and cisterns, wells, and other water systems warrant special attention; however, the assessment of these structures may be limited to surface conditions and other readily available data.
(d)The written report of the survey shall be signed by the person who conducted the survey. Copies of the report shall be promptly provided to the regulatory authority and to the person requesting the survey. If the person requesting the survey disagrees with the contents and/or recommendations contained therein, he or she may submit to both the operator and the regulatory authority a detailed description of the specific areas of disagreement.
(e)Any surveys requested more than 10 days before the planned initiation of blasting shall be completed by the operator before the initiation of blasting. \[48 FR 9807, Mar. 8, 1983, as amended at 81 FR 93392, Dec. 20, 2016; 82 FR 54979, Nov. 17, 2017\]
Connections4 cite this
Citation graph
cites case law
§ 816.62
Use of explosives: Preblasting survey.
Fed. Reg.×4
Cites 0Cited by 4 across 1 source
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.