§ 780.13. Operation plan: Blasting.
168 words·~1 min read·
/us/cfr/t30/s§ 780.13·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
(a)Blasting plan. Each application shall contain a blasting plan for the proposed permit area, explaining how the applicant will comply with the requirements of §§ 816.61 through 816.68 of this chapter. This plan shall include, at a minimum, information setting forth the limitations the operator will meet with regard to ground vibration and airblast, the bases for those limitations, and the methods to be applied in controlling the adverse effects of blasting operations.
(b)Monitoring system. Each application shall contain a description of any system to be used to monitor compliance with the standards of § 816.67 including the type, capability, and sensitivity of any blast-monitoring equipment and proposed procedures and locations of monitoring.
(c)Blasting near underground mines. Blasting operations within 500 feet of active underground mines require approval of the State and Federal regulatory authorities concerned with the health and safety of underground miners. \[48 FR 9806, Mar. 8, 1983, as amended at 81 FR 93330, Dec. 20, 2016; 82 FR 54949, Nov. 17, 2017\]
Connections22 cite this
Cited by 22 sections · top 6
Citation graph
cites case law
§ 780.13
Operation plan: Blasting.
Fed. Reg.×22
Cites 0Cited by 22 across 1 source