The Regional Supervisor may authorize subsurface storage of gas on the OCS, on and off-lease, for later commercial benefit. The Regional Supervisor may authorize subsurface storage of gas on the OCS, off-lease, for later commercial benefit. To receive approval you must:
(a)Show that the subsurface storage of gas will not result in undue interference with operations under existing leases; and
(b)Sign a storage agreement that includes the required payment of a storage fee or rental.