§ 285.905. When must I submit my decommissioning application?
104 words·~1 min read·
/us/cfr/t30/s§ 285.905·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
You must submit your decommissioning application upon the earliest of the following dates:
(a)Two
(2)years before the expiration of your lease.
(b)Ninety
(90)days after completion of your commercial activities on a commercial lease.
(c)Ninety
(90)days after completion of your approved activities under a limited lease on a ROW grant or RUE grant.
(d)Ninety
(90)days after cancellation, relinquishment, or other termination of your lease or grant.
(e)Ninety
(90)calendar days after BSEE determines a facility is no longer useful for operations. \[88 FR 6413, Jan. 31, 2023, as amended at 89 FR 42721, May 15, 2024\]
Connections8 cite this
Cited by 8 sections · top 5
Citation graph
cites case law
§ 285.905
When must I submit my decommissioning application?
Fed. Reg.×5
C.F.R.×3
Cites 0Cited by 8 across 2 sources