§ 285.708. What are the CVA's or project engineer's primary duties for fabrication and installation review?

353 words·~2 min read·/us/cfr/t30/s§ 285.708·

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

(a)The CVA or project engineer must do all of the following:
(1)Use good engineering judgment and practice in conducting an independent assessment of the fabrication and installation activities and of the commissioning of Critical Safety Systems and Equipment;
(2)Monitor the fabrication and installation of the facility and the commissioning of Critical Safety Systems and Equipment as required by paragraph
(b)of this section;
(3)Make periodic onsite inspections while fabrication is in progress and verify the items required by § 285.709;
(4)Make periodic onsite inspections while installation is in progress and satisfy the requirements of § 285.710;
(5)Certify in Project Verification Reports that project components are fabricated and installed in accordance with accepted engineering practices and to a nationally or internationally recognized quality assurance standard or to an equivalent alternate means of quality assurance considered on a case-by-case basis, your BOEM-approved SAP, COP, or GAP (as applicable), and your FIR. If multiple CVAs are involved in your project, the general project CVA must submit the final report containing such certification for the project. The Project Verification Report must identify the location of all records pertaining to facility fabrication and installation as required in § 285.714(c);
(6)Provide records documenting that Critical Safety Systems and Equipment are commissioned in accordance with the procedures identified in § 285.702(a)(8); and
(7)Identify the location of all records pertaining to commissioning of Critical Safety Systems and Equipment, as required in § 285.714(c).
(b)To comply with paragraphs (a)(4) and
(5)of this section, the CVA or project engineer must monitor the fabrication and installation of the facility and the commissioning of Critical Safety Systems and Equipment to certify that they have been built and installed according to your FDRs and FIRs.
(1)If the CVA or project engineer finds that either fabrication and installation procedures or Critical Safety Systems and Equipment commissioning procedures, or both, have been changed or design specifications have been modified, the CVA or project engineer must inform you and BSEE; and
(2)If you accept the modifications, you must also inform BSEE. \[89 FR 42718, May 15, 2024\]
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.