(a)The CVA must use good engineering judgment and practice in conducting an independent assessment of the installation activities.
(b)Primary duties of the CVA during the installation phase include the following: The CVA must . . . Operation or equipment to be inspected . . .
(1)Verify, as appropriate, ``` ```
(i)Loadout and initial flotation operations;
(ii)Towing operations to the specified location, and review the towing records;
(iii)Launching and uprighting operations;
(iv)Submergence operations;
(v)Pile or anchor installations;
(vi)Installation of mooring and tethering systems;
(vii)Final deck and component installations; and
(viii)Installation at the approved location according to the approved design and the installation plan.
(2)Witness (for a fixed or floating platform), ``` ```
(i)The loadout of the jacket, decks, piles, or structures from each fabrication site;
(ii)The actual installation of the platform or major modification and the related installation activities.
(3)Witness (for a floating platform), ``` ```
(i)The loadout of the platform;
(ii)The installation of drilling, production, and pipeline risers, and riser tensioning systems (at least for the initial installation of these elements);
(iii)The installation of turrets and turret-and-hull interfaces;
(iv)The installation of foundation pilings and templates, and anchoring systems; and
(v)The installation of the mooring and tethering systems.
(4)Conduct an onsite survey, ``` ``` Survey the platform after transportation to the approved location.
(5)Spot-check as necessary to determine compliance with the applicable documents listed in § 250.901(a); the alternative codes, rules and standards approved under § 250.901(b); the requirements listed in § 250.903 and §§ 250.906 through 250.908 of this subpart and the approved plans, ``` ```
(i)Equipment;
(ii)Procedures; and
(iii)Recordkeeping. ``` ``` ``` ``` ``` ```
(c)The CVA must submit interim reports and a final report to the Regional Supervisor, and to you, during the installation phase in accordance with the approved schedule required by § 250.911(d). In each interim and final report the CVA must: ``` ```
(1)Give details of how, by whom, and when the independent monitoring activities were conducted; ``` ```
(2)Describe the CVA's activities during the verification process; ``` ```
(3)Summarize the CVA's findings; ``` ```
(4)Confirm or deny compliance with the approved installation plan; ``` ```
(5)In the final report, make a recommendation to accept or reject the installation unless such a recommendation has been previously made in an interim report; and ``` ```
(6)Provide any additional comments that the CVA deems necessary.
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.