§ 250.1743. How do I certify that a site is clear of obstructions?
263 words·~1 min read·
/us/cfr/t30/s§ 250.1743·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
(a)For a well site, you must submit to the appropriate District Manager within 30 days after you complete the verification activities a form BSEE-0124, Application for Permit to Modify, to include the following information:
(1)A signed certification that the well site area is cleared of all obstructions;
(2)The date the verification work was performed and the vessel used;
(3)The extent of the area surveyed;
(4)The survey method used;
(5)The results of the survey, including a list of any debris removed or a statement from the trawling contractor that no objects were recovered; and
(6)A post-trawling job plot or map showing the trawled area.
(b)For a platform or other facility site, you must submit the following information to the appropriate Regional Supervisor within 30 days after you complete the verification activities:
(1)A letter signed by an authorized company official certifying that the platform or other facility site area is cleared of all obstructions and that a company representative witnessed the verification activities;
(2)A letter signed by an authorized official of the company that performed the verification work for you certifying that it cleared the platform or other facility site area of all obstructions;
(3)The date the verification work was performed and the vessel used;
(4)The extent of the area surveyed;
(5)The survey method used;
(6)The results of the survey, including a list of any debris removed or a statement from the trawling contractor that no objects were recovered; and
(7)A post-trawling job plot or map showing the trawled area.