Code · CFR · Title 30 — Mineral Resources · Part 250 · § 250.113

§ 250.113. What procedures must I follow when welding?

397 words·~2 min read·/us/cfr/t30/s§ 250.113·

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

(a)Before you weld, you must move any equipment containing hydrocarbons or other flammable substances at least 35 feet horizontally from the welding area. You must move similar equipment on lower decks at least 35 feet from the point of impact where slag, sparks, or other burning materials could fall. If moving this equipment is impractical, you must protect that equipment with flame-proofed covers, shield it with metal or fire-resistant guards or curtains, or render the flammable substances inert.
(b)While you weld, you must monitor all water-discharge-point sources from hydrocarbon-handling vessels. If a discharge of flammable fluids occurs, you must stop welding.
(c)If you cannot weld in one of the designated safe-welding areas that you listed in your safe welding plan, you must meet the following requirements:
(1)You may not begin welding until:
(i)The welding supervisor or designated person in charge advises in writing that it is safe to weld.
(ii)You and the designated person in charge inspect the work area and areas below it for potential fire and explosion hazards.
(2)During welding, the person in charge must designate one or more persons as a fire watch. The fire watch must:
(i)Have no other duties while actual welding is in progress;
(ii)Have usable firefighting equipment;
(iii)Remain on duty for 30 minutes after welding activities end; and
(iv)Maintain a continuous surveillance with a portable gas detector during the welding and burning operation if welding occurs in an area not equipped with a gas detector.
(3)You may not weld piping, containers, tanks, or other vessels that have contained a flammable substance unless you have rendered the contents inert and the designated person in charge has determined it is safe to weld. This does not apply to approved hot taps.
(4)You may not weld within 10 feet of a wellbay unless you have shut in all producing wells in that wellbay.
(5)You may not weld within 10 feet of a production area, unless you have shut in that production area.
(6)You may not weld while you drill, complete, workover, or conduct wireline operations unless:
(i)The fluids in the well (being drilled, completed, worked over, or having wireline operations conducted) are noncombustible; and
(ii)You have precluded the entry of formation hydrocarbons into the wellbore by either mechanical means or a positive overbalance toward the formation.
Connections1 cite this
Cited by 1 section
Citation graph
cites case law
§ 250.113
What procedures must I follow when welding?
Fed. Reg.×1
Cites 0Cited by 1 across 1 source
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.