Code · CFR · Title 29 — Labor · Part 3 · § 3.4

§ 3.4. Submission of certified payroll and the preservation and inspection of weekly payroll records.

351 words·~2 min read·/us/cfr/t29/s§ 3.4·

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

(a)Certified payroll. Each certified payroll required under § 3.3 must be delivered by the contractor or subcontractor, within 7 days after the regular payment date of the payroll period, to a representative at the site of the building or work of the agency contracting for or financing the work, or, if there is no representative of the agency at the site of the building or work, the statement must be delivered by mail or by any other means normally assuring delivery by the contractor or subcontractor, within that 7 day time period, to the agency contracting for or financing the building or work. After the certified payrolls have been reviewed in accordance with the contracting or sponsoring agency's procedures, such certified payrolls must be preserved by the agency for a period of 3 years after all the work on the prime contract is completed and must be produced for inspection, copying, and transcription by the Department of Labor upon request. The certified payrolls must also be transmitted together with a report of any violation, in accordance with applicable procedures prescribed by the United States Department of Labor.
(b)Recordkeeping. Each contractor or subcontractor must preserve the regular payroll records for a period of 3 years after all the work on the prime contract is completed. The regular payroll records must set out accurately and completely the name; Social Security number; last known address, telephone number, and email address of each laborer and mechanic; each worker's correct classification(s) of work actually performed; hourly rates of wages paid (including rates of contributions or costs anticipated for bona fide fringe benefits or cash equivalents thereof); daily and weekly number of hours actually worked in total and on each covered contract; deductions made; and actual wages paid. The contractor or subcontractor must make such regular payroll records, as well as copies of the certified payrolls provided to the contracting or sponsoring agency, available at all times for inspection, copying, and transcription by the contracting officer or their authorized representative, and by authorized representatives of the Department of Labor. \[88 FR 57730, Aug. 23, 2023\]
Connections10 cite this
Citation graph
cites case law
§ 3.4
Submission of certified payroll and the preservation and inspection of weekly payroll records.
Fed. Reg.×10
Cites 0Cited by 10 across 1 source
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.