§ 1000.1440. What constitutes a "significant change" in the original scope of work?
56 words·~1 min read·
/us/cfr/t25/s§ 1000.1440·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
A significant change in the original scope of work is:
(a)A change that would result in a cost that exceeds the total of the Federal project funds available and the Tribe's/Consortium's contingency funds; or
(b)A material departure from the original scope of work, including substantial departure from timelines negotiated in the construction project agreement.