The Commission, as part of the project review, shall evaluate the proposed methodology for monitoring consumptive uses, water withdrawals and mitigating flows, including flow metering devices, stream gages, and other facilities used to measure the withdrawals or consumptive use of the project or the rate of stream flow. If the Commission determines that additional flow measuring, metering or monitoring devices are required, these shall be provided at the expense of the project sponsor, installed in accordance with a schedule set by the Commission, and installed per the specifications and recommendations of the manufacturer of the device, and shall be subject to inspection by the Commission at any time.
(a)Project sponsors of projects that are approved under this part shall:
(1)Measure and record on a daily basis, or such other frequency as may be approved by the Commission, the quantity of all withdrawals, using meters or other methods approved by the Commission.
(2)Certify, at the time of installation and no less frequently than once every 5 years, the accuracy of all measuring devices and methods to within 5 percent of actual flow, unless specified otherwise by the Commission.
(3)Maintain metering or other approved methods so as to provide a continuous, accurate record of the withdrawal or consumptive use.
(4)Measure groundwater levels in all approved production and other wells, as specified by the Commission.
(5)Measure groundwater levels at additional monitoring locations, as specified by the Commission.
(6)Measure water levels in surface storage facilities, as specified by the Commission.
(7)Measure stream flows, passby flows or conservation releases, as specified by the Commission, using methods and at frequencies approved by the Commission.
(8)Perform other monitoring for impacts to water quantity, water quality and aquatic biological communities, as specified by the Commission.
(b)Reporting.
(1)Project sponsors whose projects are approved under this section shall report to the Commission on a quarterly basis on forms and in a manner prescribed by the Commission all information recorded under paragraph
(a)of this section, unless otherwise specified by the Commission.
(2)Project sponsors whose projects are approved under this section shall report to the Commission:
(i)Violations of withdrawal limits and any conditions of approvals, within 5 days of such violation.
(ii)Loss of measuring or recording capabilities required under paragraph (a)(1) of this section, within 5 days after any such loss. \[71 FR 78579, Dec. 29, 2006, as amended at 82 FR 29393, June 29, 2017\]
Connections1 cite this
Citation graph
cites case law
§ 806.30
Monitoring.
Fed. Reg.×1
Cites 0Cited by 1 across 1 source
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.