§ 7.6. Notice of acceptance and ready for environmental analysis.

238 words·~1 min read·/us/cfr/t18/s§ 7.6·

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

If the Director deems the application complete and approves the request to use the expedited licensing process under § 7.5, the Commission will issue a public notice as required in the Federal Power Act, no later than 180 days after application filing, that:
(a)Accepts the application for filing and specifies the date upon which the application was accepted for filing;
(b)Finds the application ready for environmental analysis;
(c)Requests comments, protests, and interventions;
(d)Requests recommendations, preliminary terms and conditions, and preliminary fishway prescriptions, including all supporting documentation; and
(e)Establishes an expedited licensing process schedule, including estimated dates for:
(1)Filing of recommendations, preliminary terms and conditions, and fishway prescriptions;
(2)Issuance of a draft National Environmental Policy Act
(NEPA)document, or an environmental assessment not preceded by a draft;
(3)Filing of a response, as applicable, to Commission staff's request for ESA concurrence or request for formal consultation under the ESA, or responding to other Commission staff requests to federal and state agencies, or Indian Tribes pursuant to Federal law, including the Magnuson-Stevens Fishery Conservation and Management Act and the National Historic Preservation Act;
(4)Filing of comments on the draft NEPA document, as applicable;
(5)Filing of modified recommendations, mandatory terms and conditions, and fishway prescriptions in response to a draft NEPA document or environmental assessment, if no draft NEPA document is issued; and
(6)Issuance of a final NEPA document, if any.
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.