§ 16.17. Procedures upon Congressional authorization of takeover.
86 words·~1 min read·
/us/cfr/t18/s§ 16.17·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
If Congress authorizes the takeover of a hydroelectric power project as provided under section 14 of the Federal Power Act:
(a)The Commission or the Director of the Office of Energy Projects will notify the existing licensee in writing of the authorization at least two years before the takeover occurs; and
(b)The licensee must present any claim for compensation to the Commission:
(1)Within six months of issuance of the notice of takeover; and
(2)As provided in section 14 of the Federal Power Act.